3 Installation of High-Voltage Electrical Equipment
3.1 Dominant Items
3.1.1 The commissioning test of 3-500kV GIS,ACB,OCB,handcart type oil-minimum breaker,vacuum circuit breaker,disconnecting switch,etc.shall pass the commissioning test in accordance with the requirements of Article 2.1.5 of this code.
3.1.2 Grounding of bare and non-current carrying metal parts:all the flanges shall be connected across copper strips;the ground wires of both the base and support shall be connected securely;the crosssectional areas of both copper strips and branch lines shall be correctly selected and anticorrosion protection shall be provided without omission.