2.6 Documents for Completion Acceptance of Works
2.6.1 During the completion acceptance,the signed certification shall be exchanged and the following technical documents shall be provided:
1 As-built drawings.
2 Documents related design modification and material substitution.
3 Certificates of quality for main equipment,apparatus and materials,materials list,and receiving acceptance inspection record.
4 Record of concealed works.
5 Technical documents provided with equipment.
6 Records of construction and installation.
7 Commissioning test record of electrical equipment.